First LNG Offloading via ship-to-ship transfer has been completed
The first LNG offloading via ship-to-ship transfer has been completed on last September 8th. An important phase of the project, within the commissioning of the plant, realized in line with the timing of the company, has been concluded. The activity of offloading has been started on September 2nd from the carrier LNG Leo, has been perfectly concluded. The successful completion of the operations was carried out under the supervision of the Maritime Authority and has been validated by the certification authority RINA.